Cost Breakup

Stage-Wise Construction Cost Breakup (Per Sq. Ft.)

Construction StageApprox. ShareRate (With Material)Rate (Labour Only)Key Work Covered
Up to Plinth Level12% – 15%₹250 – ₹300₹60 – ₹90Marking, excavation, PCC, footing, foundation brickwork, plinth beam, soil filling, and DPC.
Plinth to Ceiling (Superstructure)20% – 25%₹400 – ₹500₹100 – ₹140RCC columns, lintel beams, and main structural wall masonry (brick/AAC block work).
Roof Slab Casting10% – 15%₹200 – ₹300₹50 – ₹80Shuttering/centering, TMT steel bar bending, concrete pouring (M20/M25), and curing.
Walls Plastering8% – 10%₹160 – ₹200₹45 – ₹70Internal wall plaster (12mm), external double-coat plaster (18–20mm), and ceiling punning.
Remaining Finishing & MEP40% – 45%₹800 – ₹900₹150 – ₹220Flooring/tiling, plumbing, electrical wiring, doors/windows, painting, and sanitary fittings.

Quick Rules of Thumb

  • Material vs. Labour Split. Across any stage, building materials (cement, steel, sand, aggregate, bricks) account for 60% to 65% of the cost, while labour accounts for 35% to 40%.
  • Grey Structure Total. If you are only building the bare shell (up to plinth + walls + slab casting + plastering) without flooring, paint, doors, or fittings, expect to spend roughly ₹1,000 to ₹1,300 per sq. ft. with materials.
  • What is Excluded. Per-sq-ft contractor quotes generally exclude borewells, boundary walls, municipal approvals, architect fees, and underground water tanks.