Stage-Wise Construction Cost Breakup (Per Sq. Ft.)
| Construction Stage | Approx. Share | Rate (With Material) | Rate (Labour Only) | Key Work Covered |
|---|---|---|---|---|
| Up to Plinth Level | 12% – 15% | ₹250 – ₹300 | ₹60 – ₹90 | Marking, excavation, PCC, footing, foundation brickwork, plinth beam, soil filling, and DPC. |
| Plinth to Ceiling (Superstructure) | 20% – 25% | ₹400 – ₹500 | ₹100 – ₹140 | RCC columns, lintel beams, and main structural wall masonry (brick/AAC block work). |
| Roof Slab Casting | 10% – 15% | ₹200 – ₹300 | ₹50 – ₹80 | Shuttering/centering, TMT steel bar bending, concrete pouring (M20/M25), and curing. |
| Walls Plastering | 8% – 10% | ₹160 – ₹200 | ₹45 – ₹70 | Internal wall plaster (12mm), external double-coat plaster (18–20mm), and ceiling punning. |
| Remaining Finishing & MEP | 40% – 45% | ₹800 – ₹900 | ₹150 – ₹220 | Flooring/tiling, plumbing, electrical wiring, doors/windows, painting, and sanitary fittings. |
Quick Rules of Thumb
- Material vs. Labour Split. Across any stage, building materials (cement, steel, sand, aggregate, bricks) account for 60% to 65% of the cost, while labour accounts for 35% to 40%.
- Grey Structure Total. If you are only building the bare shell (up to plinth + walls + slab casting + plastering) without flooring, paint, doors, or fittings, expect to spend roughly ₹1,000 to ₹1,300 per sq. ft. with materials.
- What is Excluded. Per-sq-ft contractor quotes generally exclude borewells, boundary walls, municipal approvals, architect fees, and underground water tanks.